Planning application processing times

How long the City takes to review planning, zoning, subdivision, and building permit applications once your file is complete.

How long processing takes

Processing times start the day the City receives a complete application. They end when a decision is issued or a permit is approved. Times are estimates. They can change if we need more information, if a project is complex, or if a matter goes before Council.

Land use planning applications

Application type Standard processing time
Zoning bylaw amendment 120 calendar days
Official plan amendment 6 to 8 weeks for staff review, plus a 30-day public notice period
Major subdivision 90 calendar days
Minor subdivision 60 calendar days
Minor variance Decision at the next available Committee of Adjustment hearing
Site plan control 6 to 8 weeks
Temporary use permit 10 business days
Sign permit 5 business days
Driveway and access permit 8 to 10 weeks

For more on how to start a land use application, visit Planning applications.

Building and development permit applications

Permit type Standard processing time
Commercial or multi-family building 20 business days
Residential building (single or two-unit dwelling) 10 business days
Demolition permit 10 business days
Temporary structure or tent 10 business days
Occupancy permit 3 business days
Fire safety permit 5 business days
Tree removal permit 10 business days
Hydrant use permit 3 business days
Street use permit for construction 7 business days

Permit processing times assume all drawings, reports, and fees are submitted correctly. If plans need changes, the clock stops until we receive the updated documents.

What affects processing time?

  • Completeness: Incomplete files are returned or put on hold. A $125.00 completeness check fee applies to planning files returned for missing information.
  • Complexity: Large developments, heritage projects, or sites near the Tamsin River floodplain take longer to review.
  • Public notice: Applications that require mailing neighbours or posting signs on site add time. The City usually posts a 30-day notice for zoning and subdivision changes.
  • Council schedule: Applications that go before Council or the Committee of Adjustment follow meeting dates. You can check the Council meeting schedule for upcoming dates.
  • External reviews: Some files need reviews from Tamsin Valley Public Health, the Tamsin Valley Conservation Authority, or utility providers. These reviews run at the same time as City staff reviews but can add a few weeks.

Check your application status

You can track your file online using the Find a planning application. The tool shows your application number, current stage, and any staff comments. If you need help or have a question about your file, email the planning and development team at [email protected] or call the City at 519-555-0100.